The chalet roofed, mid-December
The chalet roofed, mid-December
E.1

Raising a chalet.

My role
Assembly, as a team
SIA phases 52
2012

A solid-timber log chalet, assembled as a team from September to December 2012 in the pine forest of Piquey, on the Cap Ferret peninsula, on the sand of a dune. Delivered in numbered parts, the house is put together in three months, from the foundation pads to the roof tiles.

LocationLocation
Location
Piquey, Lège-Cap-Ferret (33)
Programme
Solid-timber chalet
Setting
Family property
Role
Assembly, as a team
Year
2012
SIA 112 phasesFrance: Site work

Foundations and platform.

No slab on the dune: concrete pads cast in cardboard formwork at the bearing points only, then a joist frame that lifts the house above the sand. The natural ground and the pines stay in place, the floor is ventilated from below and the slope is taken up in the height of the pads; a single decision settles moisture, terrain and respect for a fragile site.

Foundation piers in the sand
Foundation piers in the sand
The joist frame on the piers
The joist frame on the piers

Log walls.

Grooved logs, notched to cross at the corners, stacked without nails or posts: the ground floor goes up in a day, and from the first courses every partition, every opening reads on the ground like a plan at 1:1. The structure is also the interior finish, with no second phase of works to hide the first. The one requirement: the timber still settles by a few centimetres as it dries, and the windows and doors must absorb it.

First rows of logs
First rows of logs
Corner joint of the logs
Corner joint of the logs
The ground floor at the end of the day
The ground floor at the end of the day

Roof frame and covering.

The purlins rest directly on the log gables and overhang generously to shelter the façades from the rain. Rafters, a temporary tarpaulin, a breather membrane, then interlocking tiles laid by hand on battens, from eaves to ridge: the house is weathertight, then airtight, within a few weeks, a speed that rests entirely on what was prepared beforehand.

Purlins and first rafters
Purlins and first rafters
Gable and rafters
Gable and rafters
Under the rafters
Under the rafters
Temporarily weathertight
Temporarily weathertight
Breathable membrane and windows
Breathable membrane and windows
Laying the tiles
Laying the tiles
Full portfolio (PDF, 39 pp., in French)