A.2
Landeyeux.
Nursing home, Fontaines (NE)
- My role
- Project manager, planning
- SIA phases 41 · 51
- 2025–2026
Extension and conversion of the nursing home: timber façades punctuated by light bands, planted courtyard, entrance under a wide canopy. I organised the tendering of the fit-out works and followed the production of the pre-construction drawings.
- Location
- Fontaines (NE)
- Client
- Landeyeux Foundation
- Programme
- Nursing home, extension and conversion, 140 beds
- Cost
- 80 M CHF
- Architect
- Fahrny & Partenaires SA
- Role
- Project manager, planning
- Period
- 2025–2026
SIA 112 phases
19 lots, 5 packages, one cycle.
Nineteen CFC lots grouped into five packages, from writing the specifications to receiving the bids, aligned with the client’s fortnightly meetings. Schedule kept in MS Project.
The tender package: general specifications for buildings A and B, the annex and the underground car park, contractor lists, then bid comparisons by CFC code.
19Finishing-trade packages
5Staggered batches
30 jTypical cycle of a package, from launch to receipt of bids
13Packages running in the busiest week
- Document production
- Approvals
- Contractor consultation
- Client meeting
Time counted in weeks from the launch of the first package · based on the tender schedule kept in MS Project